Thursday, October 29, 2009

Partial Repair Work on Scott near Clay next Monday

Driveway access to this garage will be restricted from
Monday to Wednesday.
Scott at Clay
The contractor will replace a defective street panel outside 2203 Scott Street next Monday.
Vallejo & Van Ness
Test 24-inch water transmission line next Monday and Tuesday.

Friday, October 23, 2009

Repaving on Pacific and Steiner Finished Thursday

The water and sewer replacement, and street renovation for Pacific Avenue was completed after workers repaved two blocks between Steiner and Scott streets Thursday, October 22nd. Steiner between Pacific and Jackson was also repaved on the same day.
Other activities in the area:
Scott at Clay
The contractor will replace defective street panel on the west side of Scott from Thursday, October 28th through Saturday, October 31st.
Vallejo at Van Ness
Water Department will perform test for the newly-installed 24-inch water transmission line Thursday, October 29th and Friday, October 30th.

Thursday, October 22, 2009

Scott Street Repaving between Jackson and Pacific Thursday

The repaving will be complete in one day as the crew shown here makes its way down Pacific Avenue at the intersection of Scott and Jackson streets Thursday morning.

Monday, October 19, 2009

Two Curb Ramp Constructions at Scott Street

One of the Scott Street's curb ramp constructions at Pacific Avenue Monday.

The contractor is working on new curb ramp constructions on Scott Street at the intersections of Washington Street and Pacific Avenue from Monday to Wednesday. Other constructions in the area:

Pacific - Steiner & Scott
Final repaving Thursday and Friday.
Steiner - Pacific & Jackson
Final repaving Thursday and Friday.
Clay and Divisadero
Excavate 24-inch connection hole on Monday.

Tuesday, October 13, 2009

Reconstruction of Center Panel of Scott Street

There is no construction work on Scott at Washington
Monday, October 13th due to bad weather.

Scott Street
* Clay & Jackson
* Street reconstruction (center panel) Monday to Wednesday.
* At Washington and at Pacific
Rebuild curb ramps all week.
Steiner - Pacific & Jackson
The 24-inch transmission line connection will be complete by Wednesday or Thursday.

Friday, October 2, 2009

Weekend Work on Scott and Washington

Worker Claude Frazier preparing for the weekend work on Scott Street Friday morning.

To speed up the street restoration process, the contractor will be working on Saturday, October 3rd repaving the sidewalk on the east side (at the park) of Scott Street near Washington Street There will be no parking or traffic flow restrictions. Work hours will be from 8 am to 6 pm.

Thursday, October 1, 2009

Final Repaving at Vallejo Street

Workers began repaving Vallejo street starting at the corner of Van Ness Avenue Friday morning .
Following installations of a new sewer line and a water main, the contractor has started the final process of street renovation of three blocks on Vallejo Street from Octavia Street to Van Ness Avenue Friday.

Other activities in the area:
Scott – Clay & Jackson
* Near Washington Street - sidewalk construction on Saturday, October 3rd from 8 am to 6 pm.
* Curb and sidewalk restoration (east side near the park) – continue all week.
* Reconstruct curb ramps – continue all week
* at Scott and Washington
* at Scott and Pacific
Steiner – Pacific & Jackson
The Water Department’s 24-inch connection work should finish by Monday, October 5th, to be followed by final repaving on this block as well as Pacific Avenue from Steiner to Scott streets later this month.
Union – Larkin & Leavenworth
Construction work continues through next Wednesday.
Filbert – Mason & Taylor
Excavation work all week.