In addition, learn how San Francisco is working to get clean power, how you can harvest rainwater and save energy and money!
Tuesday, December 29, 2009
Sign up for SFPUC's new Digital Currents Newsletter and Enter to Win Prize!
In addition, learn how San Francisco is working to get clean power, how you can harvest rainwater and save energy and money!
Thursday, December 17, 2009
Clay Street Final Repaving is Underway Thursday
The final process of repaving on Clay Street between the intersections of Scott and Divisadero streets has begun Thursday morning, which will complete the construction of a new water line in this neighborhood. The water line installation is part of the SFPUC’s Water System Improvement Program (WSIP), a combination of new water mains, sewer repairs and replacement, and pavement renovation. A joint undertaking between the SFPUC and the Department of Public Works, the North University Mound System Upgrade project will provide a backup water supply to this area in case of an emergency, reduce service interruption or repairs, and prevent sewer backups and overflows.The WSIP project team wants to thank the neighbors for their patience throughout the construction and wish everyone a happy holiday and a prosperous new year.
Tuesday, December 15, 2009
Final Repaving at Clay Scheduled for Thursday
Friday, December 11, 2009
Monday, December 7, 2009
Wednesday, November 25, 2009
Friday, November 20, 2009
Water Line Connection at Divisadero and Clay About to Complete
The connection work for the 24-inch water transmission line at this intersection continues Friday and expects to finish next Monday.Tuesday, November 17, 2009
Friday, November 13, 2009
Final Repaving for Vallejo and Larkin
Workers repave Vallejo Street between Van Ness Avenue and Larkin Street Thursday, completing the water transmission line construction for this block.Union - Larkin/Leavenworth
The Water Department's disinfection and connection works for the newly-installed water transmisson line will continue throughout next week.
Thursday, October 29, 2009
Partial Repair Work on Scott near Clay next Monday
Friday, October 23, 2009
Repaving on Pacific and Steiner Finished Thursday
The water and sewer replacement, and street renovation for Pacific Avenue was completed after workers repaved two blocks between Steiner and Scott streets Thursday, October 22nd. Steiner between Pacific and Jackson was also repaved on the same day. The contractor will replace defective street panel on the west side of Scott from Thursday, October 28th through Saturday, October 31st.
Water Department will perform test for the newly-installed 24-inch water transmission line Thursday, October 29th and Friday, October 30th.
Thursday, October 22, 2009
Monday, October 19, 2009
Two Curb Ramp Constructions at Scott Street
The contractor is working on new curb ramp constructions on Scott Street at the intersections of Washington Street and Pacific Avenue from Monday to Wednesday. Other constructions in the area:
Pacific - Steiner & Scott
Final repaving Thursday and Friday.
Steiner - Pacific & Jackson
Final repaving Thursday and Friday.
Clay and Divisadero
Excavate 24-inch connection hole on Monday.
Tuesday, October 13, 2009
Reconstruction of Center Panel of Scott Street
* Clay & Jackson
* Street reconstruction (center panel) Monday to Wednesday.
* At Washington and at Pacific
Rebuild curb ramps all week.
Steiner - Pacific & Jackson
The 24-inch transmission line connection will be complete by Wednesday or Thursday.
Friday, October 2, 2009
Weekend Work on Scott and Washington
Thursday, October 1, 2009
Final Repaving at Vallejo Street
Scott – Clay & Jackson
* Near Washington Street - sidewalk construction on Saturday, October 3rd from 8 am to 6 pm.
* Reconstruct curb ramps – continue all week
* at Scott and Washington
* at Scott and Pacific
Steiner – Pacific & Jackson
The Water Department’s 24-inch connection work should finish by Monday, October 5th, to be followed by final repaving on this block as well as Pacific Avenue from Steiner to Scott streets later this month.
Construction work continues through next Wednesday.
Filbert – Mason & Taylor
Excavation work all week.
Friday, September 25, 2009
Sidewalk Reconstruction on Scott from Clay to Jackson
The east side of Scott Street near Jackson Street during reconstruction Friday afternoon.Scott Street – Clay/Jackson
Curb and sidewalk restoration (east side near the park) – on-going all week.
* Reconstruct curb ramps:
1. at Scott and Washington
2. at Scott and Pacific
The contractor is completing the final phase of street restoration on this section of Vallejo Street.
* Franklin to Van Ness - On-going concrete paving will be completed by Monday, September 28, to be followed by final asphalt paving in the second week of October.
* Gough to Franklin - On-going driveway reconstruction will be completed by Monday, September, 28th, to be followed by final asphalt paving in the second week of October.
* Octavia to Gough – Final street paving in the second week of October.
* Vallejo at Van Ness - Access ramp restoration on the west side of Vallejo will be finished by Friday, September 25th or Monday, September 28th.
Pacific and Steiner
The Water Department will be connecting water lines the week of September 28th.
Friday, September 18, 2009
Driveway Restriction on Vallejo between Gough and Van Ness
* Gough and Franklin
Driveway construction has begun Thursday, September 17. Garages will NOT be accessible on Monday, September 21st, between 8 am and 6 pm. Work will continue on some driveways after Monday, however access will be provided.
*Franklin and Van Ness
Driveway construction has begun Friday, September 18th. Garages will NOT be accessible for one more day on Monday, September 21st, between 8 am and 6 pm. Work will continue on some driveways after Monday, however access will be provided.
Other construction activities in the vicinity:
2. Intersection of Union and Hyde
Two more weekends of work on:
* September 19th and 20th between 7 a.m. to 8 p.m.
* September 26th and 27th between 7 a.m. to 8 p.m.
Weekends are the only time MUNI can de-energize its buses so that construction work can proceed at this intersection.
4. Pacific and Steiner
The Water Department is making connections through next Friday.
For more information contact Ben Chan bychan@sfwater.org or call 415-554-3284, or cell 415-306-4592. After hours and weekends call 415-550-4911.
Tuesday, September 15, 2009
No Driveway Access on the South Side of Vallejo between Franklin and Van Ness
Construction crew working Tuesday to prepare for this Friday’s driveway restoration.Friday, September 11, 2009
Construction Update on Vallejo between Gough and Van Ness
* Pipe-testing - The Water Department will have finished testing and making connections by Friday, September 11th.
2. Vallejo at Van Ness - Restoring curb ramp on the west side of the intersection through September 25th.
3. Union
* Larkin to Hyde - The contractor will finish installing 24-inch and 8-inch water tranmission lines next Monday.
* Hyde to Leavenworth – The contractor will install 24-inch and 8-inch water transmission lines from Tuesday to Friday.
* At the intersection of Hyde – Crews will be working over 3 consecutive weekends starting September 12th through September 27th. Weekends are the only time MUNI can de-energize buses so that construction work can proceed at this intersection. After the tunneling work under the cable car tracks has been completed, the contractor will install and connect a 24-inch water transmission line, which will take about a week.
For more information, contact Ben Chan at 415-554-3284, or 415-306-4592, or email bychan@sfwater.org
Tuesday, September 8, 2009
Driveway Restoration Underway at Vallejo between Franklin and Van Ness
The work crew started restoring driveways Tuesday morning.* Tuesday 8th: Driveways reconstruction on the north side of Vallejo between Franklin and Van Ness. Driveway will be accessible.
* Wednesday 9th: Pour curb. Driveway will be accessible.
* Thursday 10th: Pour driveway. To allow the concrete enough time to dry up, the garages will NOT be accessible to the residents between 8 am to 6 pm.
Please make arrangements accordingly. If you have special needs or an emergency situation, the inspector on site will work with you. You may also call Ben Chan of SFPUC Communications at 415-554-3284 or 415-306-4592. Driveway restoration for the opposite side of this block will be scheduled very soon.
Driveway Restoration Underway For Vallejo Street

As part of the final phase of the combined water main and sewer replacement, and street renovation, the contractor is working on driveway restoration on Vallejo Street between Franklin Street and Van Ness Avenue. This is the schedule:
* Tuesday 8th: Demolition of curbs and driveways on the north side of Vallejo between Franklin and Van Ness. Driveway will be accessible.
* Wednesday 9th: Pour curb. Driveway will be accessible.
*Thursday 10th: Pour driveway. To allow the concrete enough time to dry, the garages will NOT be accessible between 8 am to 6 pm.
Please make arrangements accordingly. If you have special needs or an emergency situation, the inspector on site will work with you. You may also call Ben Chan of SFPUC Communications at 415-554-3284 or 415-306-4592.
Friday, September 4, 2009
No Construction During Labor Day Long Weekend
Construction activities next Tuesday to Friday:
1. Vallejo / Franklin & Van Ness
The north side of this portion of Vallejo will go through driveway and curb ramp repair from Tuesday to Thursday. The schedule is as follows:
Tuesday 8th - Demolish driveways (driveway accessible)
Wednesday 9th - Pour curb (driveay accessible)
Thursday 10th - Pour driveway (No driveway access between 8AM and 6PM)
2. Vallejo / Gough & Van Ness
The Water Department will
*continue to test pipes and make seven 8-inch connections to the residents throughout next week.
*connect 12-inch conenction at Franklin from Wednesday to Friday.
3. Pacific / Steiner
The Water Department will make 24-inch water transmission connection throughout next week.
Wednesday, September 2, 2009
Repaving of Pacific Avenue Soon to be Complete
Thursday, August 27, 2009
Scott Street Driveway / Street Restoration Update
By around 12 pm Friday, more than half of the west side of Scott between Washington and Clay streets are poured with concrete.8 am Monday, August 31 to 4 pm Saturday, September 5.
To help accommodate residents who will not have access to driveways and garages, their vehicles will be allowed to park along the east side of Scott Street. One-lane traffic will be limited to local residents only.
Wednesday, August 26, 2009
Street Parking For Residents on Scott Street
Vehicle access to this section of Scott between Clay and Washington will be limited to local residents only.To help accommodate residents who will not have access to driveways and garages on Scott between Clay and Washington from Wednesday, August 26th to Monday, August 31st, we have made the following arrangements:
Residents’ vehicles will be allowed to park along the east side of Scott Street at the park. One-way traffic will be limited to local residents only.
We apologize for the inconvenience and are doing everything we can to minimize the impact to our neighbors. Cooperation from our neighbors will help us finish our work as quickly as possible.
If you have special needs or an emergency situation, the inspector on site will work with you. You may also call Ben Chan of SFPUC Communications at 415-306-4592.
Thursday, August 20, 2009
Driveway Repaving on Scott between Clay and Washington
1. Scott Street
Notices have been sent out to residents on Scott between Clay and Jackson advising them that their driveways will be scheduled to be poured. In order for the cement to dry up residents will not be able to access their driveways on certain days.
4 pm Monday, August 31.
* Scott between Washington and Jackson - Driveways on this block will not be accessible from:
* The contractor will also build a new curb ramp at the corner of Scott and Clay next Tuesday and Wednesday.
* The contractor will finish installing concrete street panel on the west side of Scott from Clay to Jackson next Wednesday to Friday.
Other construction activities next week:
2. Vallejo & Van Ness
The contractor will install a curb ramp at Vallejo on the west side of Van Ness next Wednesday to Friday.
3. Pacific / Steiner
The Water Department will make 24-inch water transmission connection all week.
4. Pacific / Fillmore
The Water Department continues to test pipe and making connection to the residents next Monday to Wednesday.
North Beach
1.Filbert / Mason & Leavenworth
Install 24-inch water line from:
* Mason to Taylor this Friday and next Monday.
* Taylor to Jones next Tuesday to Friday.
2. Larkin / Vallejo & Union
Install 24-inch water line from:
* Vallejo to Green this Friday and next Monday to Tuesday.
* Green to Union this Friday and next Wednesday to Friday.
3. Saturday work at Larkin / Union intersection
The contractor will work at this location as weekend is the only time MUNI can de-energize its buses so that construction work can proceed at this intersection.
Friday, August 14, 2009
Water Main Installation on Vallejo to Larkin
Trenching along Vallejo Street between Van Ness and Larkin to prepare for installing a 24-inch water transmission line next Monday to Wednesday.North Beach area:
1. Vallejo / Van Ness to Larkin
Install 24-inch water transmission line between Van Ness and Polk, from Monday to Wednesday.
2. Larkin / Vallejo to Union
Install 24-inch water transmission line from /Vallejo to Green from Thursday and Friday.
3. Filbert / Columbus & Mason
Excavate and install vault next Monday; install 24-inch water transmission line from Tuesday to Thursday.
Cow Hollow/Pacific Height area:
1. Vallejo / Gough & Van Ness
The contractor will dig up locations so that the Water Department can test pipes and make connections to the residents throughout next week.
2. Pacific / Steiner
The Water Department will make 24-inch water transmission connections from Monday to Wednesday.
3. Pacific / Fillmore
The Water Department is completing testing pipe and making connections to the residences this Friday, August 14th.
4. Scott / Clay & Jackson
The contractor will reapir driveways and sidewalk on the west side of Scott from Clay to Jackson all week.
The contractor will repair sidewalk and ramp all week.
6. Clay / Divisadero & Scott
Wednesday, August 12, 2009
Tuesday, August 11, 2009
Sidewalk/Driveway Repairs and Street Repaving in Full Swing
Grinding work on the slope section of Scott and Washington streets Tuesday, August 11.Beginning the second week of August through the end of the month, the contractor is repairing sidewalks, driveways, and repaving streets at various sections of Scott, Broadway, Vallejo, and Pacific Avenue.
Friday, August 7, 2009
Repaving on Pacific Avenue
Repaving on Pacific Avenue between Pierce and Scott streets is part of the final process of sewer and water main constructions in the Pacific Height area as the contractor plans to do the same for nearby streets that have gone through similar upgrades.Other construction activities next week:
1. Vallejo / Gough & Van Ness
The Water Department is testing and cleaning pipelines and making connections to the residents, to be followed by sidewalk repair and street repaving next week.
2. Scott / Jackson & Clay
The contractor will start repaving next week and will continue through mid-September.
3. Pacific / Steiner
The Water Department will make 24-inch water main connections next week, to be followed by repaving.
4. Filbert / Mason & Leavenworth
Intall 24-inch water main next Wednesday to Friday.
5. Vallejo / Van Ness & Larkin
Install 24-inch water main from Van Ness to Polk from Monday to Wednesday; Polk to Larkin from Wednesday to Friday.
Wednesday, August 5, 2009
Repaving Scott between Jackson and Clay
The intersection of Scott and Jackson is ready for final repavingFriday, July 31, 2009
WSIP Moves to Polk Street Area Early August
The intersection of Van Ness and Vallejo looking toward Larkin As we begin to wrap up construction in the Pacific Heights/Cow Hollow area, the combined water and sewer construction will move to Vallejo Street between Van Ness Avenue and Larkin Street starting next Wednesday. Please let us know how to make this project more neighbor friendly by visiting this blog at sfwater.org/district2 or call Ben Chan at 415-306-4592.
Thursday, July 30, 2009
Two-way traffic is maintained on Broadway Street while repaving continues. Other construction activities next week:
1. Vallejo / Franklin & Van Ness:
* Vallejo from Gough to Van Ness
* The contractor will test 8-inch water main this Friday and next Monday and excavate the connection on Tuesday
* The Water Department will chlorinate and make connections to residents from Tuesday to Friday.
2. Broadway/Octavia and Pacific/Steiner
The contractor will make the 24-inch water main connections between these two locations
all week.
3. Scott / Jackson & Clay
* The contractor continues potholing, followed by chlorinating lines and making connections at Scott/Clay to Pacific /Fillmore all week.
* Scott / Washington & Clay – Continues installing electronic devices to monitor water quality this Friday and next Monday.
4. Filbert / Mason & Columbus
Water main trenching work begins next Wednesday through Friday.
5. Vallejo at Larkin
Begin excavating trench, laying 24-inch sewer pipe, and installing a new manhole.
Wednesday, July 29, 2009
Making Service Connections at Pacific Avenue
Tuesday, July 28, 2009
Last Phase of Water Pipeline Project Moves to North Beach
Starting next week, the contractor will begin underground work and laying a new water main using trenchless methods across the intersection of Filbert and Mason streets. The work will commence on approximately Monday, August 3rd. Paving work will follow after completion of the water work in the area. This is the last segment of the North Unversity Mound System Upgrade Project that is scheduled to be completed near year's end.
Friday, July 24, 2009
New Driveways for Webster Street Residents
This driveway on Webster Street will be repaved next WednesdayOther construction activities in the area next week:
1. Vallejo / Franklin & Van Ness : Continue testing 24-inch water main from Van Ness to Broadway/Octavia next Monday and Tuesday, install 54-inch sewer main and replace side sewer next Monday; install service lines from Tuesday to Thursday; and make connections to homes on Wednesday.
2. Scott / Jackson & Clay : Potholing, chlorination and making connections to homes continue from Pacific/Fillmore to Scott/Clay.
3. Scott / Washington & Clay : Continue installing electronic devices called Supervisory Control and Data Acquisition to monitor water quality.
Friday, July 17, 2009
Sidewalk Improvements on Vallejo Street
Residents on Vallejo Street near Octavia will notice improvements as workers are replacing the sidewalk, curb and gutter. Several driveway improvements will also be included in this work.
1. Vallejo / Franklin & Van Ness : Test 24-inch water main from Van Ness to Broadway/Octavia between Tuesday and Friday; excavate trench and install 54-inch sewer pipe.
2. Scott / Jackson & Clay : The Water Department crew starts chlorination and will make service connections to homes. This will require some potholing.
3. Scott / Washington & Clay : Install electronic devices to monitor water quality.
Friday, July 10, 2009
Sidewalk Repaving on Vallejo Near Octavia Street
Other construction activities in the area next week:
1. Vallejo / Octavia & Gough : Chlorination test for the new water main and main connections at Broadway/Octavia to Vallejo/Gough ; Dig up curbs and ramps for repaving work.
2. Vallejo / Franklin & Van Ness : Excavate trench and install 54-inch sewer line.
3. Scott / Jackson & Clay : Excavate connection locations to allow the Water Department to chlorinate and make connections.
4. Clay / Divisadero & Scott : Excavate trench, install and pressure-test 24-inch water main at Clay and Divisadero to Pacific and Steiner next Monday to Wednesday.
Thursday, July 2, 2009
Vallejo/ Franklin & Van Ness Water Main and Sewer Constructions
Construction at Vallejo Street between Franklin Street and Van Ness Avenue will continue throughout the month of July Water main : Our contractor will excavate trench and install 24-inch and 8-inch water mains next Monday. From Wednesday to Friday, crew will test a 24-inch water main at Broadway and Octavia.
Sewer replacement: Excavating trench and installing 54-inch sewer line from Tuesday to Friday.
Other construction activities in the area:
1. Vallejo / Octavia & Gough : Chlorination test and make connections at Broadway/Octavia to Vallejo/Gough throughout next week.
2. Scott / Jackson & Clay : Excavating trench and installing 8-inch water main next Monday to Wednesday.
3. Pacific / Fillmore to Scott & Clay : Testing 8-inch new water main next Thursday and Friday.
4. Clay / Divisadero & Scott : Saw-cut, excavate trench and install 24-inch water line next Thursday and Friday.
Saturday, June 27, 2009
Clay/Divisadero & Scott Water Main Construction
Other construction activities in the area next week:
1. Vallejo Street’s construction next Monday through Thursday:
A. Vallejo / Octavia & Gough : Chlorination testing at Broadway/Octavia to Vallejo/Gough next Monday through Thursday.
B. Vallejo / Franklin & Van Ness :
* Excavate trench and install 24-inch and 8-inch water mains.
* Make connection from the 54-inch sewer line to existing manhole.
C. Vallejo / Franklin & Gough : Temporary paving next Monday through Wednesday.
2. Pacific / Fillmore & Scott : Test 8-inch new water main next Monday.
3. Scott /Jackson to Clay : Excavate trench and install 8-inch water main next Monday and Tuesday; install services Wednesday and Thursday.
Friday, June 19, 2009
Vallejo / Franklin & Van Ness Water Main and Sewer Pipe Installation
saw-cut, excavate trench, and install 24-inch and 8-inch water main pipes all week.
Other construction updates in the vicinity next week:
2. Pacific / Fillmore & Scott : Testing 8-inch new water main next Monday and Tuesday.
Friday, June 12, 2009
Scott/Jackson Saturday Work, June 13
Other construction updates in the vicinity next week:
1. Scott/ Jackson & Clay : Saw cutting, excavating trench and installing 8-inch water main all week.
2. Pacific / Pierce & Scott : Testing 8-inch new water main next Monday and Tuesday—some parking restricted.
3.Vallejo / Gough to Broadway/ Octavia : Testing 8-inch new water main next Monday and Tuesday –some parking restricted.
4. Vallejo / Franklin intersection : Installing 8-inch water main next Monday and Tuesday.
5. Vallejo / Franklin & Van Ness : Saw-cutting street next Tuesday.
6. Vallejo / Franklin : Installing 24-inch water transmission line next Monday to Wednesday.
7. Vallejo / Van Ness : Installing 24-inch water transmission line next Thursday and Friday.
8. Vallejo / Octavia & Gough : Temporary paving next Wednesday and Thursday.
Friday, June 5, 2009
Full Week of Water Main Work on Scott Street between Pacific Avenue and Jackson Street
Work at other locations next week:
1. Pacific / Fillmore & Scott: Test 8-inch new water main next Monday and Tuesday.
2. Vallejo / Gough & Franklin: Excavate trench and install 24-inch and 8-inch water lines next Monday and Tuesday.
3. Vallejo / Van Ness: Install 24-inch water transmission line all week.
4.Vallejo / Octavia & Gough : Temporary paving next Thursday and Friday.
Friday, May 29, 2009
Water main construction on Pacific Avenue moves uphill from Pierce to Scott streets
Work at other locations next week :
1. Scott and Clay: Sewer replacement work begins this week involving saw cutting, excavate trench and construct new manhole
2. Vallejo at Franklin : Puts 24-inch water transmission line into the ground
3. Vallejo at Van Ness : Installs 36-inch casing.
4. Vallejo/ Gough & Octavia : No work for the next two weeks
Thursday, May 21, 2009
Neighbors Cooperation Appreciated
Neighbors truly accommodating with limited garage access
We appreciate residents’ patience and support in areas where the project work has caused us to limit access to your garages. These will not be common occurrences. Thank you again for your cooperation.
Construction update on Pacific Avenue and other areas
This week the contractor has been removing abandoned rail at Pacific Avenue between Steiner and Pierce streets and the same work will reach the intersection of Scott Street next Wednesday. On-going excavating, saw-cutting work and installing water and sewer pipelines will continue in the same area.
Work at other locations next week :
1. Vallejo at Franklin : On-going jack and bore under the street and installing 36-inch casing
2. Vallejo – Gough & Octavia : On-going. Excavating trench and installing 24-inch and 8-inch pipes will begin next Tuesday.
Tuesday, May 19, 2009
Work Moves Towards Van Ness Avenue
Workers start trenching outside 1699 Vallejo Street Tuesday morning, May 19th.Begining Tuesday, the contractor starts excavating at Vallejo Street at Franklin Street to install water pipelines. This same work has been ongoing at Vallejo Street between Franklin and Gough streets since Wednesday, May 13th and will continue through this week. Work at other locations this week:
1. Vallejo – Gough & Octavia : Install side sewers Monday and Tuesday.
3. Pacific - Steiner & Pierce : RemoveJabandoned rail and then excavate trench. Tuesday through Friday.
Friday, May 8, 2009
Webster between Green and Lombard completed
1. Vallejo/Franklin & Octavia : On-going. Shore, excavate trench and install side sewers.
Friday, May 1, 2009
Vallejo between Franklin and Octavia
1. Pacific/Fillmore & Steiner : Excavating trench and laying 24-inch ductile iron pipe between Fillmore & Steiner streets.
2. Pacific/Steiner & Pierce : Continue to remove abandoned rail next Wednesday to Friday.
3. Webster/Lombard & Filbert : Grinding and paving will take place next Tuesday and Wednesday, completing the Webster segment of sewer and water construction.
4. Scott/Washington & Pacific : Installing side sewers and culverts.
Friday, April 24, 2009
Pacific/Fillmore Saturday Work, April 25th
1. Pacific/Webster & Fillmore : Temporary paving on Thursday & Friday and will continue through Monday.
2. Pacific/ Webster & Pierce : The contractor plans to finish removing abandoned rail between Webster and Fillmore this week and will do the same next week between Steiner and Pierce. The contractor has the option of closing off the street but residents can access their driveways at all times.
3. Webster/Lombard & Filbert : aving will begin next Monday. This is the final stretch of work between Lombard and Green.
4. Vallejo/Gough & Octavia : Sewer work, including saw-cutting, excavating trench, removing existing sewer and installing side sewer, begins this Friday and will continue for a week.
Friday, April 17, 2009
Wesbter/Lombard Night Work Monday April 20th
Lombard and Webster streets intersection.2. Pacific/Fillmore & Steiner : Removing abandoned railway track will continue next week.
3. Pacific/Webster & Steiner : Contractor will install a 24-inch water transmission line early next week.
4. Webster/Broadway & Pacific : Service connections to the buildings continue.
5. Webster/Lombard to Green : Pavement restoration continues.


























