* Pipe-testing - The Water Department will have finished testing and making connections by Friday, September 11th.
2. Vallejo at Van Ness - Restoring curb ramp on the west side of the intersection through September 25th.
3. Union
* Larkin to Hyde - The contractor will finish installing 24-inch and 8-inch water tranmission lines next Monday.
* Hyde to Leavenworth – The contractor will install 24-inch and 8-inch water transmission lines from Tuesday to Friday.
* At the intersection of Hyde – Crews will be working over 3 consecutive weekends starting September 12th through September 27th. Weekends are the only time MUNI can de-energize buses so that construction work can proceed at this intersection. After the tunneling work under the cable car tracks has been completed, the contractor will install and connect a 24-inch water transmission line, which will take about a week.
For more information, contact Ben Chan at 415-554-3284, or 415-306-4592, or email bychan@sfwater.org