Our contractor will be working at the intersection of Pacific Avenue and Fillmore Street this Saturday, April 25th. The weekend is the only time MUNI can take buses off-line so that construction work can proceed. Other construction updates in the vicinity include:
1. Pacific/Webster & Fillmore : Temporary paving on Thursday & Friday and will continue through Monday.
2. Pacific/ Webster & Pierce : The contractor plans to finish removing abandoned rail between Webster and Fillmore this week and will do the same next week between Steiner and Pierce. The contractor has the option of closing off the street but residents can access their driveways at all times.
3. Webster/Lombard & Filbert : aving will begin next Monday. This is the final stretch of work between Lombard and Green.
4. Vallejo/Gough & Octavia : Sewer work, including saw-cutting, excavating trench, removing existing sewer and installing side sewer, begins this Friday and will continue for a week.