Friday, April 3, 2009

Saturday Work on Pacific; Street Updates

To finish the sewer installation, the contractor will be working Saturday, April 4 on Pacific between Fillmore and Steiner. Saturday is the only time, MUNI will take the electrical buses out of operation.
In other areas of Pacific Heights, work will continue at current locations:

1. Webster/Green & Lombard : Water Department crew continues to make final connections to the residential buildings and chlorinate the line through the end of the week.
2. Octavia/Vallejo & Gough : The contractor is installing a 24-inch water transmission line through mid-week.
3. Broadway/Laguna & Octavia : Sewer work will take place throughout the week.
4. Pacific/Webster & Steiner : End of the week, the crew will remove a rail in Pacific Avenue and then excavate the trench for the 24" water line. This work will continue through 4/22.
5. Scott/ Pacific & Jackson : New sewer installation will progress to this point.