Saturday, June 27, 2009

Clay/Divisadero & Scott Water Main Construction

Our contractor will start saw-cutting, excavating and installing 24-inch water main next Wednesday and Thursday.

Other construction activities in the area next week:
1. Vallejo Street’s construction next Monday through Thursday:

A. Vallejo / Octavia & Gough : Chlorination testing at Broadway/Octavia to Vallejo/Gough next Monday through Thursday.
B. Vallejo / Franklin & Van Ness :
* Excavate trench and install 24-inch and 8-inch water mains.
* Make connection from the 54-inch sewer line to existing manhole.
C. Vallejo / Franklin & Gough : Temporary paving next Monday through Wednesday.
2. Pacific / Fillmore & Scott : Test 8-inch new water main next Monday.
3. Scott /Jackson to Clay : Excavate trench and install 8-inch water main next Monday and Tuesday; install services Wednesday and Thursday.

Friday, June 19, 2009

Vallejo / Franklin & Van Ness Water Main and Sewer Pipe Installation

The intersection of Vallejo and Franklin is closed off for
a busy week of construction
Our contractor will excavate trench and install a 54-inch sewer pipe;
saw-cut, excavate trench, and install 24-inch and 8-inch water main pipes all week.

Other construction updates in the vicinity next week:
1. Scott/ Jackson & Clay : Continue saw cutting, excavating trench and installing 8-inch water main all week.
2. Pacific / Fillmore & Scott : Testing 8-inch new water main next Monday and Tuesday.

Friday, June 12, 2009

Scott/Jackson Saturday Work, June 13

Site of Saturday work at the intersection of Jackson and Scott streets
Our contractor will be working at the intersection of Scott and Jackson streets this Saturday, June 13th. The weekend is the only time MUNI can take buses off-line so that construction work can proceed.

Other construction updates in the vicinity next week:
1. Scott/ Jackson & Clay :
Saw cutting, excavating trench and installing 8-inch water main all week.
2. Pacific / Pierce & Scott : Testing 8-inch new water main next Monday and Tuesday—some parking restricted.
3.Vallejo / Gough to Broadway/ Octavia : Testing 8-inch new water main next Monday and Tuesday –some parking restricted.
4. Vallejo / Franklin intersection : Installing 8-inch water main next Monday and Tuesday.
5. Vallejo / Franklin & Van Ness : Saw-cutting street next Tuesday.
6. Vallejo / Franklin : Installing 24-inch water transmission line next Monday to Wednesday.
7. Vallejo / Van Ness : Installing 24-inch water transmission line next Thursday and Friday.
8. Vallejo / Octavia & Gough : Temporary paving next Wednesday and Thursday.

Friday, June 5, 2009

Full Week of Water Main Work on Scott Street between Pacific Avenue and Jackson Street

The intersection of Scott and Jackson streets is closed
for upcoming water main work
Next week the contractor starts saw-cutting, excavating trenches and installing 24-inch and 8-inch water lines on Scott Street between Pacific Avenue and Jackson Street. The removal of abandoned railway track along Pacific Avenue is completed.

Work at other locations next week:
1. Pacific / Fillmore & Scott: Test 8-inch new water main next Monday and Tuesday.
2. Vallejo / Gough & Franklin: Excavate trench and install 24-inch and 8-inch water lines next Monday and Tuesday.
3. Vallejo / Van Ness: Install 24-inch water transmission line all week.
4.Vallejo / Octavia & Gough : Temporary paving next Thursday and Friday.