Friday, June 12, 2009

Scott/Jackson Saturday Work, June 13

Site of Saturday work at the intersection of Jackson and Scott streets
Our contractor will be working at the intersection of Scott and Jackson streets this Saturday, June 13th. The weekend is the only time MUNI can take buses off-line so that construction work can proceed.

Other construction updates in the vicinity next week:
1. Scott/ Jackson & Clay :
Saw cutting, excavating trench and installing 8-inch water main all week.
2. Pacific / Pierce & Scott : Testing 8-inch new water main next Monday and Tuesday—some parking restricted.
3.Vallejo / Gough to Broadway/ Octavia : Testing 8-inch new water main next Monday and Tuesday –some parking restricted.
4. Vallejo / Franklin intersection : Installing 8-inch water main next Monday and Tuesday.
5. Vallejo / Franklin & Van Ness : Saw-cutting street next Tuesday.
6. Vallejo / Franklin : Installing 24-inch water transmission line next Monday to Wednesday.
7. Vallejo / Van Ness : Installing 24-inch water transmission line next Thursday and Friday.
8. Vallejo / Octavia & Gough : Temporary paving next Wednesday and Thursday.