The east side of Scott Street near Jackson Street during reconstruction Friday afternoon.Scott Street – Clay/Jackson
Curb and sidewalk restoration (east side near the park) – on-going all week.
* Reconstruct curb ramps:
1. at Scott and Washington
2. at Scott and Pacific
The contractor is completing the final phase of street restoration on this section of Vallejo Street.
* Franklin to Van Ness - On-going concrete paving will be completed by Monday, September 28, to be followed by final asphalt paving in the second week of October.
* Gough to Franklin - On-going driveway reconstruction will be completed by Monday, September, 28th, to be followed by final asphalt paving in the second week of October.
* Octavia to Gough – Final street paving in the second week of October.
* Vallejo at Van Ness - Access ramp restoration on the west side of Vallejo will be finished by Friday, September 25th or Monday, September 28th.
Pacific and Steiner
The Water Department will be connecting water lines the week of September 28th.