The work crew starting process to restore driveways Tuesday morning.
As part of the final phase of the combined water main and sewer replacement, and street renovation, the contractor is working on driveway restoration on Vallejo Street between Franklin Street and Van Ness Avenue. This is the schedule:
* Tuesday 8th: Demolition of curbs and driveways on the north side of Vallejo between Franklin and Van Ness. Driveway will be accessible.
* Wednesday 9th: Pour curb. Driveway will be accessible.
*Thursday 10th: Pour driveway. To allow the concrete enough time to dry, the garages will NOT be accessible between 8 am to 6 pm.
Please make arrangements accordingly. If you have special needs or an emergency situation, the inspector on site will work with you. You may also call Ben Chan of SFPUC Communications at 415-554-3284 or 415-306-4592.
Driveway restoration on the opposite side of this block will be scheduled very soon.