Friday, February 27, 2009

Vallejo between Franklin and Octavia

The Water Department responded to and repaired a water main leak on Webster Street at Pacific Avenue at about 7:30 am Friday, February 27. Water supply was restored to the residents at about 10 am.

Shaw Pipeline will begin sewer construction on Vallejo Street between Franklin and Octavia streets starting Monday, March 2nd while the water main construction on Broadway Street between Buchanan and Laguna streets will continue as scheduled.

Wednesday, February 25, 2009

Webster between Buchanan and Laguna

Water main construction workers setting up new pipes on Broadway Street between Buchanan and Laguna streets yesterday.

The contractor has started water main construction on Broadway Street between and Buchanan and Laguna streets while the work outside Hamlin School is expected to complete by the end of February, 2009. The crew will come back at a later time for paving of that section of the street.

Sunday, February 22, 2009

Hamlin School


Water main construction work on Broadway and Buchanan streets.

To accommodate the parents of Hamlin School dropping off their children on Monday, February 23rd after the school’s one-week break, two-lane traffic in both directions will be maintained on Broadway Street between Webster and Buchanan streets until 8:30 am. The contractor plans to complete the water main construction on that block no later than Tuesday, February 24th.

Tuesday, February 17, 2009

Broadway Between Webster & Buchanan Streets

Construction crew is preparing to open up Broadway Street between Webster and Buchanan streets this week.

The contractor will start construction outside Hamlin School (left), taking advantage of the school’s one-week break.

Friday, February 13, 2009

Construction crew is busy at the intersection of Webster and Lombard streets.

The contractor will open up the intersection of Webster and Lombard streets this week and expects to meet the construction schedule without adding night work hours. On the other hand, to reduce impacts to parents and students, a second crew will start working on Broadway Street between Webster and Octavia streets next week when the Hamlin School takes a one-week break from the President’s Day.

Tuesday, February 10, 2009

Excavation work on Webster and Broadway streets.

The contractor is installing water service connections to the buildings on Webster Street between Broadway Street and Pacific Avenue this week. Meanwhile saw cutting work also starts on Broadway Street between Webster and Octavia streets.

The contractor will need to do some night work on Webster and Lombard streets next week at the earliest. We will confirm as soon as we have definite dates. Let us know your comments and suggestions for making this project more neighborhood friendly.

Tuesday, February 3, 2009

A worker swept the intersection of Webster and Union streets Saturday morning while a police officer (background) directed traffic.

After the contractor finished installing an 8-inch water main through the intersection at Webster and Union streets on Saturday, January 31, construction this week focuses on excavating a trench at Webster and Green streets.