Wednesday, November 25, 2009

Connection Work Complete at Divisadero and Clay

A worker directing traffic Wednesday morning was waiting for the work crew to come and finish the water line connection work at this intersection.

Friday, November 20, 2009

Water Line Connection at Divisadero and Clay About to Complete

The connection work for the 24-inch water transmission line at this intersection continues Friday and expects to finish next Monday.
The water line replacement work in this area is about to complete very soon. The San Francisco Public Utilities Commission wants to take this time to thank the neighbors for their patience and cooperation and to wish everyone a very Happy Thanksgiving.

Tuesday, November 17, 2009

Water Line Connection Work at Clay and Divisadero

The Water Department is making connections Tuesday for the newly-installed water transmission line at the intersection of Clay and Divisadero streets, where three-way traffic is maintained. The crew expects to complete the work by next Monday.

Friday, November 13, 2009

Final Repaving for Vallejo and Larkin

Workers repave Vallejo Street between Van Ness Avenue and Larkin Street Thursday, completing the water transmission line construction for this block.
Other construction activities in the area:
Union - Larkin/Leavenworth
The Water Department's disinfection and connection works for the newly-installed water transmisson line will continue throughout next week.

Tuesday, November 3, 2009

Repair to the defective street panel outside 2203 Scott Street is complete but to allow the concrete to cure, access to the driveway is restricted until 5 pm Wednesday, November 4th.