Friday, September 4, 2009

No Construction During Labor Day Long Weekend

The contractor will have no construction in the Cow Hollow/Pacific Height area next Monday, September 7.

Construction activities next Tuesday to Friday:

1. Vallejo / Franklin & Van Ness
The north side of this portion of Vallejo will go through driveway and curb ramp repair from Tuesday to Thursday. The schedule is as follows:

Tuesday 8th - Demolish driveways (driveway accessible)
Wednesday 9th - Pour curb (driveay accessible)
Thursday 10th - Pour driveway (No driveway access between 8AM and 6PM)

2. Vallejo / Gough & Van Ness
The Water Department will
*continue to test pipes and make seven 8-inch connections to the residents throughout next week.
*connect 12-inch conenction at Franklin from Wednesday to Friday.

3. Pacific / Steiner
The Water Department will make 24-inch water transmission connection throughout next week.