a busy week of construction
Our contractor will excavate trench and install a 54-inch sewer pipe;
saw-cut, excavate trench, and install 24-inch and 8-inch water main pipes all week.
saw-cut, excavate trench, and install 24-inch and 8-inch water main pipes all week.
Other construction updates in the vicinity next week:
1. Scott/ Jackson & Clay : Continue saw cutting, excavating trench and installing 8-inch water main all week.
2. Pacific / Fillmore & Scott : Testing 8-inch new water main next Monday and Tuesday.
2. Pacific / Fillmore & Scott : Testing 8-inch new water main next Monday and Tuesday.