for upcoming water main work
Next week the contractor starts saw-cutting, excavating trenches and installing 24-inch and 8-inch water lines on Scott Street between Pacific Avenue and Jackson Street. The removal of abandoned railway track along Pacific Avenue is completed.
Work at other locations next week:
1. Pacific / Fillmore & Scott: Test 8-inch new water main next Monday and Tuesday.
2. Vallejo / Gough & Franklin: Excavate trench and install 24-inch and 8-inch water lines next Monday and Tuesday.
3. Vallejo / Van Ness: Install 24-inch water transmission line all week.
4.Vallejo / Octavia & Gough : Temporary paving next Thursday and Friday.
Work at other locations next week:
1. Pacific / Fillmore & Scott: Test 8-inch new water main next Monday and Tuesday.
2. Vallejo / Gough & Franklin: Excavate trench and install 24-inch and 8-inch water lines next Monday and Tuesday.
3. Vallejo / Van Ness: Install 24-inch water transmission line all week.
4.Vallejo / Octavia & Gough : Temporary paving next Thursday and Friday.