Friday, May 1, 2009

Vallejo between Franklin and Octavia

On-going work at Vallejo Street between Gough and Octavia
will continue next week.

The contractor’s work next week concentrates on the sewer construction at Vallejo Street between Franklin and Octavia streets, including excavating trench and removing existing brick sewer. Other on-going construction updates:

1. Pacific/Fillmore & Steiner : Excavating trench and laying 24-inch ductile iron pipe between Fillmore & Steiner streets.
2. Pacific/Steiner & Pierce : Continue to remove abandoned rail next Wednesday to Friday.
3. Webster/Lombard & Filbert : Grinding and paving will take place next Tuesday and Wednesday, completing the Webster segment of sewer and water construction.
4. Scott/Washington & Pacific : Installing side sewers and culverts.