Friday, August 7, 2009

Repaving on Pacific Avenue

Repaving on Pacific Avenue between Pierce and Scott streets is part of the final process of sewer and water main constructions in the Pacific Height area as the contractor plans to do the same for nearby streets that have gone through similar upgrades.

Other construction activities next week:

1. Vallejo / Gough & Van Ness
The Water Department is testing and cleaning pipelines and making connections to the residents, to be followed by sidewalk repair and street repaving next week.
2. Scott / Jackson & Clay
The contractor will start repaving next week and will continue through mid-September.
3. Pacific / Steiner
The Water Department will make 24-inch water main connections next week, to be followed by repaving.
4. Filbert / Mason & Leavenworth
Intall 24-inch water main next Wednesday to Friday.
5. Vallejo / Van Ness & Larkin
Install 24-inch water main from Van Ness to Polk from Monday to Wednesday; Polk to Larkin from Wednesday to Friday.